January 28, 2011

W5_Abiola Ojo_Selecting a Cost Estimating Methodology for a School Building Project

Problem Statement
On my proposed school building project, I desire to carry out a cost estimate of the project to enable me predict the final cost of the project. The cost estimate will assist me in making sound investment decision and cash-flow projection. This estimate will also form the basis for my budgets, progress measurement, trending, forecasting, and change management. The school project is just at the conceptual stage and I need to make an investment decision within two months. Before I can proceed with the cost estimation however, I need to decide on the estimating methodology that will best meet my objectives knowing well that several estimating methodologies exist.  

Alternatives
In choosing the best cost estimating methodology for the project, three cost estimating methodologies were evaluated:

Alternative 1: Order-of-magnitude estimate
Alternative 2: Budget or semi-detailed estimate
Alternative 3: Definitive or detailed estimate


Outcome of the Alternatives

Alternative 1: Order-of-magnitude estimate
This method involves the use of historical data from similar projects to estimate the cost of the project by modifying those data for changes in inflation or deflation, activity level, location, productivity, cost of labour, dimensions, and other factors.   
    Estimate Accuracy: -30/+50%
Cost of Estimation + Pre-work: $1,000
Estimate Timeline + Pre-work: 2 week

Alternative 2: Semi-detailed estimate
This method will require some preliminary engineering and details and will require the services of a professional. This is usually a factored estimate based on major equipment costs.
    Estimate Accuracy: -15/+30%
Cost of Estimation + Pre-work: $2,500
Estimate Timeline + Pre-work: 4 weeks

Alternative 3: Detailed Estimate
This is a very detailed method of cost estimating and requires breaking down the project into small, manageable units. These unit costs are rolled up into the overall cost estimate. The method requires a high level of project definition including specifications, drawings, site surveys, and vendor quotations and will usually require a professional team to carry it out.
    Estimate Accuracy: -5/+15%
Cost of Estimation + Pre-work: $6,000
Estimate Timeline + Pre-work: 8 weeks 


Selection Criteria

S/N
Criteria
Weight
1
Estimate Accuracy
1
2
Cost of Estimation + Pre-work
3
3
Estimate Timeline + Pre-work
2


Analysis of Alternatives

Alternative
Estimate Accuracy

Cost of Estimation

Timeline
Ranking
Weight
1
3
2
Alternative 1
1
3
3
15
Alternative 2
2
2
2
12
Alternative 3
3
1
1
8
Key: Best - 3, Fair - 2, Worst - 1

Alternative Selected
Based on the above analysis, Alternative 1 which isOrder-of-magnitude estimate had the highest ranking is therefore the selected alternative at this stage of the project.

Performance Monitoring
Actual cost of estimation and schedule will be tracked against budget in order to evaluate performance. Performance based payment (Earned Value Methodology) will be used for paying the contractor.

References
Engineering Economy, 14th Edition. Chapter 1, Page 27 & Chapter 3, Page 91-102 William G. Sullivan, Elin M. Wicks, C. Patrick Koelling

2 comments:

  1. Biola.......!!! Uh oh!!! You did a really nice job picking a real problem and you set it up very nicely and did your comparison, BUT......

    I gotta REJECT it..... Why? Turn to your Skills and Knowledge, Appendix F. Then you explain to me WHY I rejected this posting and am asking that you redo do it as W5.1.

    Now, remember that I told you I was expecting that you cite at least 3 references? And that I expected you to be relying on the materials I provided to you? Can you begin to understand WHY I did this and why for the future, you would be very wise to make certain that you are using the latest standards? (FWIW, PMI is still using the old ANSI Z-94 standard, but most oil and gas companies dropped that close to 20 years ago when they started to adopt the phase gated asset management life span approach.)

    But it was well written, but unfortunately, it was wrong.... (And be sure to know what is in RP 18R-97, as it will almost SURELY be on one or more of your exams)

    BR,
    Dr. PDG, Jakarta

    ReplyDelete
  2. This is very interesting....while reading,i was very impressed and was hoping to see excellent from DR PDG...unfortunately,am seeing this....well, we want to attain world class

    ReplyDelete