February 15, 2011

WK#11_IDUBAMO MONIGHA_THE CHOICE OF NATURAL GAS CONDENSATE EVACUATION TECHNIQUE IN ONE OF THE MAJOR GAS FIELDS IN NIGERIA’S NIGER DELTA.

Problem Statement

The incessant attacks and uncontrollable bunkering activities on the existing condensate evacuation line has become a serious burden to the government and its JV partners. This is most common in swampy terrains and therefore needs immediate replacement of the existing line.

However, the greatest challenge is what type of evacuation technique most suitable to avert bunkering and devastation of the environment. A timeline of 18 months has been given as expected completion period.

Root Cause Analysis

Fatalities as a result of illegal bunkering fires.

Pollution of environment and frequent forest fires.

Evacuation line integrity check indicates line can no longer be in use.

Line is over 25 years old.

Low gas from gas fields to gas plant

Short supply of feed gas from gas plant to LNG plant

Line has over identified 650 bunkering points

Spiking not accepted option by government regulators.

Alternatives:

Alternative A: Burial of evacuation line using trenchless technique.

Alternative B: Burial of evacuation line with concrete mat and concrete tunnel technique.

Alternative C: Burial of evacuation line using normal shallow trenches.

Alternative D: Transport condensate via barging.

Analysis of Alternatives

Alternative A: Trenchless technique - This requires the laying of 8’’ x 10km Carbon steel pipeline using horizontal directional drilling technique.

http://www.northeasttrenchless.com/dw2.jpg

Courtesy of http://www.northeasttrenchless.com/hdd.html

CAPEX Costs

Right of way acquisition – Not required

Environmental Impact Assessment – $0.15M

Engineering and Design

Route Survey – $0.11M

Geotechnical investigation - $1.5M

FEED and Detailed Design - $0.76M

Procurement

Cost of Linepipes, PE coating and Concrete coating - $3.8M

Construction

Pipeline installation using HDD burial - $8M

Pipeline testing and commissioning - $0.3M

Project Management Contractor – $0.22M

Owners Cost - $0.52M

Contingencies - $1.6M

Total Project Cost - $17M

Schedule

Duration – 8Months

Annual OPEX Costs

$0.7M

MERITS

No surface river crossings

Short duration of execution.

Lesser impact to the environment.

Few persons involved in construction

Little equipment required on site

No surveillance on line

Deep burial which reduces exposure to bunkering activities.

Low security cost during construction

Surface distortion is eliminated

Low cost of environmental restoration as against trenching.

Low safety risk exposure

Low cost of Project management

DEMERITS

No tie-ins allowed

High cost of execution.

HDD equipment not available in-country.

Execution of HDD by imported expertise.

Lack of technology transfer to locals through engineering, procurement and construction.

Expensive cost of repair when pipeline is damaged.

Repair of damaged portion takes a long time; requires deployment of HDD equipment to salvage and repair.

Approval process by regulatory authorities takes longer; due to its rare usage.

Alternative B: This requires the laying of a 10’’ x8km Carbon steel pipeline in a deep excavation with concrete mat footing and concrete tunnel on top in pipeline.

CAPEX Costs

Right of way acquisition – Not required

Environmental Impact Assessment – $1.42M

Engineering and Design

Route Survey – $0.11M

Geotechnical investigation - $0.65M

FEED and Detailed Design - $0.34M

Procurement

Cost of Linepipes, PE coating and Concrete coating - $3.8M

Cost of Pre-cast concrete mats/tunnels - $2M

Construction

Concrete mat/tunnel installation - $2.9M

Pipeline installation - $1.76M

Pipeline testing and commissioning – $0.30M

Project Management Contractor – $1.44M

Owners Cost - $0.73M

Contingencies - $1.4M

Total Project Cost - $15.41M

Schedule

Duration – 24Months

Annual OPEX Costs

$0.9M

MERITS

Unhindered approval by regulatory authority

In country capacity involved in Engineering, Procurement and Construction

90% Local capacity in installation

Low surveillance on line

Deep burial which reduces exposure to bunkering activities.

DEMERITS

High cost of execution.

Expensive cost of repair when pipeline is damaged.

Repair of damaged portion takes a longer time; requires destruction of concrete protection to access line

High environmental impact during construction

Long execution period

Involves a lot of workforce both onsite and offsite

Plenty of equipment required

High cost of project management

High safety risk exposure level during construction

Very high cost of surface restoration.

High cost of security

Alternative C: This requires the laying of a 10’’ x 8km Carbon steel pipeline in shallow trenches.

CAPEX Costs

Right of way acquisition – Not required

Environmental Impact Assessment – $0.42M

Engineering and Design

Route Survey – $0.11M

Geotechnical investigation - $0.26M

FEED and Detailed Design - $0.17M

Procurement

Cost of Linepipes, PE coating and Concrete coating - $3.8M

Construction

Pipeline installation - $2.67M

Pipeline testing and commissioning - $0.3M

Project Management Contractor – $0.6M

Owners Cost - $0.54M

Contingencies - $1M

Total Project Cost - $9M

Schedule

Duration – 18Months

Annual OPEX Costs

$1.8M

MERITS

Low cost of execution

Short execution duration

Low cost of repairs (via existing call-out contract)

Unhindered approval by regulatory authority

In country capacity involved in Engineering, Procurement and Construction

100% Local capacity in installation

DEMERITS

Susceptible to bunkering

High environmental impact during construction

Involves a lot of workforce both onsite and offsite

Plenty of equipment required

High cost of project management

High safety risk exposure level during construction

High cost of surface restoration.

High Surveillance of line.

High cost of security during construction.

Alternative D: This requires the evacuation of condensate using barging means.

CAPEX Costs

Right of way acquisition – Not required

Environmental Impact Assessment – N0.35M

Engineering and Design

FEED and Detailed Design - $0.09M (discharging and receiving facilities MOD works).

Procurement

Procurement of Floating Storage and offloading (FSO) barge - $28M

Construction

Capital dredging for barging route and floating storage offloading vessels - $6M

Flowstations modification works for discharge/receiving facilities – $1m

Project Management Contractor – $0.26M

Owners Cost - $0.52M

Contingencies - $3.5M

Total Project Cost - $40M

Schedule

Duration – 12Months

Annual OPEX Costs

Mtce dredging, security, Loading, barging and discharging (1yr duration x $11m pa)

MERITS

Short execution duration

In country capacity involved in Engineering, Procurement and Construction of facilities modification

100% Local capacity in modification works

Low cost of project management

DEMERITS

Mobilisation of FSO barge from outside country

Stringent approval because of the transportation of hydrocarbon in-country

Susceptible to pirates attack

Very high security alert level and cost

High environmental impact if accidented or attacked

High river traffic along river route

Plenty of equipment required

High cost of project management

High safety risk exposure level during transportation

SELECTION CRITERIA

Value Drivers – Deter Bunkering activities, Opex <$2M, Low environmental impact (during and after construction), speedy approval by regulatory authority, duration not exceeding 18months, utilization of local content through EPC, Capex < $30M, low security exposure and low repairs cost

Using Grid Analysis

Using Grid Analysis

GRID ANALYSIS (UNWEIGHTED)

Alternatives

Drivers

OPEX < $2M

CAPEX < $30M

LOCAL CONTENT

ENVIRONMENT IMPACT

APPR BY REGULATOR

PRJ DURATION > 18MTH

REPAIR COST

DETER BUNKERING ACTIVITIES

SECURITY THREAT

A

5

5

1

5

1

5

1

5

5

B

5

5

3

1

3

1

1

3

3

C

5

5

5

3

5

3

5

1

1

D

1

1

1

3

1

5

3

5

3

LEGEND

High impact

1

medium impact

3

Low impact

5

GRID ANALYSIS (WEIGHTED)

Alternatives

OPEX < $2M

CAPEX < $30M

LOCAL CONTENT

ENVIRONMENT IMPACT

APPR BY REGULATOR

PRJ DURATION > 18MTH

REPAIR COST

DETER BUNKERING ACTIVITIES

SECURITY THREAT

TOTAL

Weighting

3

3

3

4

3

3

3

4

3

A

15

15

3

20

3

15

3

20

15

109

B

15

15

9

4

9

3

3

12

9

79

C

15

15

15

12

15

9

15

4

3

103

D

3

3

3

12

3

15

9

20

9

77

LEGEND Order of importance

Very high

4

High

3

Medium

2

Low

1

Selection of Preferred Alternative.

Based on the value drivers listed and grid analysis above. Alternative A ranked highest in score therefore is the preferred alternative.

Performance montoring and post-evaluation

Approval by regulatory body can be fast-tracked by conducting in-depth study and obtaining results of similar installation globally.

Installation of a computerized LDS (leak detection system) along line for easy detection via GPRS.

Installation of pig traps and periodic pigging of line.

The promotion of trenchless technology by the Local content monitoring board for condensate line burial, as seen all over for road crossings.

References:

The memory jogger 2 ‘Tool for continuous improvement and effective planning by Michael Brassard and Diane Ritter – Second Edition 2010.

Foundation design and Construction by MJ Tomlinson, Seventh edition 2001

http://www.mindtools.com/pages/article/newTED_03.htm

http://www.mindtools.com/pages/article/newTMC_80.htm

http://www.northeasttrenchless.com/hdd.html

1 comment:

  1. WOW!!!! AWESOME!!! Idubamo, you understand exactly what we are looking to have you learn. The only "weak" part is if you had access to your Engineering Economy, you could have produced an even more sophisticated analysis using the tools and techniques of multi-attribute decision making (Chapter 14) but otherwise, there is nothing at all wrong with your approach.

    Keep up the good work and if you can, it would be great if you would assist your colleagues in writing up their blog postings? For each person you help catch up, I am willing to give you credit for that week in return for you taking the time to mentor your colleagues.

    BR,
    Dr. PDG, Jakarta

    ReplyDelete