February 3, 2011

WK#9_IDUBAMO MONIGHA_THE CHOICE OF POWER SUPPLY OPTION TO A MAJOR RIVERINE COMMUNITY IN NIGERIA’S NIGER DELTA WITHIN NEXT 15 MONTHS.

Problem Statement

The riverine communities of Nigeria’s Niger Delta contribute a large percentage of Nigeria’s oil and gas. Up till date a great majority are without electricity; whereas the oil facilities glow with lightings in their midst. As a panacea to this age long neglect, the government has mandated oil companies to utilize fared gas in generating power to these communities to improve infrastructure.

In compliance with the government steer on utilization of flared gas to power, the need for a workable option is now sort in advicing the operators of the oil/gas production around these communities.

Root Cause Analysis

Agitation by communities through blockage of supplies and frequent shutting down of facilities;

Militancy resulting in low production and damage to facilities.

Poor rural infrastructure.

Environmental degradation.

Stoppage of gas flaring.

High unemployment rate.

Huge amount spent annually on diesel for generators in community ($8m Opex).

Alternatives:

Alternative A: Power generated with Gas Turbine Generators at operator production facility and power transmitted via submarine cable to Communities.

Alternative B: Power generated with Gas turbine Generators at operator facility and power transmitted via overhead transmission.

Alternative C: Gas Turbine Generators located in community, gas transmitted via pipeline from operator facility and power evacuated through substation only.

Analysis of Alternatives

Alternative A: This requires the installation of 2no x 2.5MW gas turbines (GT) at operator facility and laying of 20km 33KV submarine cable from the generating facility to the community.

CAPEX Costs

Right of way acquisition for additional 5km canals - $0.5m

Environmental Impact Assessment - $0.6M

Engineering and Design

Hydrographic survey - $0.5m

Subsea Survey Works - $1M

FEED and Detailed Design - $1.1M

Procurement

Cost of Turbines - $6M

Cost of submarine cable - $12M

Construction

Installation of Turbines - $3M

River dredging and construction of canals to allow vessel navigation - $8m

Submarine Cable installation - $15M

Brownfield works at Facility (to allow gas processing and intake) - $3.1M

Project Management Contractor - $1.1M

Owners Cost - $1M

Contingencies - $4M

Total Project Cost - $57.4M

Schedule

Duration – 18 Months

Annual OPEX Costs

$1.8M

MERITS

Short duration for execution.

Lesser impact on environment.

Maintenance and operation of GT Turbine by Operator.

GT Turbine in relatively secure location.

Lesser persons involved in construction.

Cable burial by subsea burial tool.

Cable stringing and tensioning by cable-lay vessel.

No surveillance on line

No periodic maintenance on line

Cable not exposed for easy theft

Low security cost during construction

DEMERITS

High cost of cable

High cost of execution.

Lay-vessel not available in-country.

Cable to be wholly imported.

Execution of cable-lay largely by imported expertise.

Cable susceptible to damage through dredging, fishing, anchoring by vessels and drop objects.

Lack of technology transfer to locals through engineering, procurement and construction.

Expensive cost of repair when cable is damaged.

Repair of damaged portion takes a long time; requires deployment of repair vessel from outside country.

Difficulty in navigation by lay-vessel and route is not an open river.

Stringent approval process by regulatory authorities.

Alternative B: This requires the installation of 2no x 2.5MW gas turbines (GT) at operator facility and installation of 10km 33KV overhead transmission system from the generating facility to the community.

CAPEX Costs

Right of way acquisition for overhead transmission (10Km) - $0.1m

Environmental Impact Assessment - $0.45M

Engineering and Design

Route Survey - $0.3M

Geotechnical works - $0.2M

FEED and Detailed Design – $1.2M

Procurement

Cost of Turbines - $6M

Cost of Overhead line cables - $0.2M

Construction

Installation of Turbines - $3M

Pylons construction (pylon procurement, fabrication and installation including foundations) – $23M

Brownfield works at Facility (to allow gas processing and intake) - $0.9M

Project Management Contractor - $1.4M

Owners Cost - $1M

Contingencies - $0.9M

Total Project Cost - $38.3M

Schedule

Duration – 12 Months

Annual OPEX Costs

$2.7M

MERITS

Low cost of cable

Cable manufactured in-country

Shorter duration for execution.

Maintenance and operation of GT Turbine by Operator.

GT Turbine in relatively secure location.

100% Local capacity in transmission engineering, procurement and construction

Fault easily detected

Low cost of repair on line.

Repair works done over a short duration

Low contingency

Easy approval process by regulatory authorities

Line not easily susceptible to damage.

DEMERITS

Involves large workforce and high safety exposure

Tower erection time consuming

Cable stringing done manually.

Cumbersome stringing/pylons construction process along mangrove route.

Frequent surveillance along route

Periodic maintenance

High rate of cable theft resulting in power interruption

High cost of security during construction

High environmental impact during construction

Alternative C: This requires the installation of 2no x 2.5MW gas turbines (GT) in the community and laying of 5km gas pipeline operator gas manifold to the community.

CAPEX Costs

Right of way acquisition not required – on existing right of way

Environmental Impact Assessment - $1.5M

Engineering and Design

Route survey – $0.4M

FEED and Detailed Design – $1.56M

Procurement

Cost of Turbines - $6M

Linepipes/fittings - $3.5M

Linepipes coating - $0.4M

Construction

Installation of Turbines - $3M

Pipeline construction – $1.2M

Site preparation works/sand filling at community - $11M

Gas processing Facility at community - $3.3M

Project Management Contractor - $1.4M

Owners Cost - $1M

Contingencies - $3.5M

Total Project Cost - $41.5M

Schedule

Duration – 9 Months

Annual OPEX Costs

$4M

MERITS

No power transmission from operator facility

Shorter duration for execution.

100 % Local capacity in engineering and construction

Fault easily detected

Low cost of repair on line.

Repair works done over a short duration

DEMERITS

100% procurement of linepipes out of country, in-country mill capacity overburdened.

Involves large workforce and high safety exposure

GT Turbine and gas processing facility security not under operator control.

A no-pass by regulatory authority – Gas line/facility in community

Frequent surveillance along route

Maintenance and operation of Turbine by community

Periodic maintenance

High rate of vandalism resulting in power interruption and operator facility shutdown

High cost of security during and after construction

High environmental impact during and after construction

SELECTION CRITERIA

Value Drivers – Opex <$2M, Low environmental impact (during and after construction), speedy approval by regulatory authority, duration not exceeding 15months, utilization of local content through EPC, lesser interface between operator facility and community, Capex < $50M, low security exposure and low repairs cost

Using Grid Analysis

GRID ANALYSIS (UNWEIGHTED)

Alternatives

Drivers

OPEX < $2M

CAPEX < $50M

LOCAL CONTENT

ENVIRONMENT IMPACT

APPR BY REGULATOR

PRJ DURATION > 15MTH

REPAIR COST

GEN SETS AND PROCESS FACILITY EXPOSURE

SECURITY EXPOSURE

A

5

1

1

5

1

1

1

5

5

B

3

3

5

3

5

3

5

5

3

C

1

3

3

1

3

5

3

1

1

LEGEND

High impact

1

medium impact

3

Low impact

5

GRID ANALYSIS (WEIGHTED)

Alternatives

Value Drivers

OPEX < $2M

CAPEX < $50M

LOCAL CONTENT

ENVIRONMENT IMPACT

APPR BY REGULATOR

PRJ DURATION > 15MTH

REPAIR COST

GEN SETS AND PROCESS FACILITY EXPOSURE

SECURITY EXPOSURE

Total

Weighting

4

4

5

3

5

4

4

4

3

A

20

4

5

15

5

4

4

20

15

92

B

12

12

25

9

25

12

20

20

9

144

C

4

12

15

3

15

20

12

4

3

88

LEGEND - Magnitude of importance

High

5

medium

3

Low

1

Selection of Alternative

Based on the value drivers listed and grid analysis above. Alternative B ranked highest in score therefore is the recommended alternative.

Recommendation

Environmental impact assessment is done to ascertain level of effect and mitigation carried out.

Engage community to partner on surveillance of line to increase security.

Drive opex down by handing over transmission line to public electricity authority.

Stakeholders engaged on time to carry everyone along and deter unnecessary show stoppers.

References:

The memory jogger 2 ‘Tool for continuous improvement and effective planning by Michael Brassard and Diane Ritter – Second Edition 2010.

http://www.mindtools.com/pages/article/newTED_03.htm

http://www.mindtools.com/pages/article/newTMC_80.htm

http://www.contactenergy.co.nz/web/pdf/our_projects/waikatowindfarm/june2008/R02_HMR_Transmission_System_Consideration_of_Alternative_Appendix8.pdf

1 comment:

  1. Much better, Idubamo!!! The only part keeping you from earning a WOW!!! was Step 7..... You totally missed explaining to us how you plan on monitoring and controlling the project..... Or the PRODUCT of the project....

    And when you get your Engineering Economy, you will see additional, more sophisticated methods in Chapter 14..... But plenty of time to learn how to use those tools and techniques in the coming weeks.

    In the meantime, you are definitely on the right track and your level of sophistication in understanding and applying the tools and techniques is getting noticeably better...... So carry one and looking forward to another sophisticated presentation next week!!

    BR,
    Dr. PDG, Jakarta

    ReplyDelete