Problem Statement
As part of the process for making a final investment decision for my school business, I had to conduct a risk analysis on the project uncertainties in other to understand the possible deviations from the expected outcome. Risks are typically defined as negative events, such as losing money on a venture or a storm creating large insurance claims.
Alternatives or Methods
In evaluating the project risks, three quantitative methods were used namely: Deterministic Analysis, Monte Carlo Simulation, and Tornado Diagram.
- Deterministic Analysis: This method uses single-point estimates of risk by assigning values for discrete scenarios to see what the outcome might be in each. In this study, three different outcome were examined: worst case, best case, and most likely case. The uncertainty parameters analyzed in this study were: initial capital, operating expenditure, number of students enrolled, school fees, and loan interest rate. For each of these parameters, values were given for three cases as shown in Fig 1. These values are based on a combination of historic data and actual market prices. Outcomes analyzed were NPV and IRR.
![]() |
Fig 1 |
- Monte Carlo Simulation: In this method, values are sampled at random from the input probability distributions. Each set of samples is called an iteration, and the resulting outcome from that sample is recorded. Monte Carlo simulation does this hundreds or thousands of times, and the result is a probability distribution of possible outcomes. The resulting data is plot in a chart showing the different outcomes and their chances of occurrence. In this study, the variables: initial capital, operating expenditure, number of students enrolled, school fees, and loan interest rate were used to calculate the outcome which is yearly profit. Random values were generated for each of the variables from the range shown in Fig 1. The simulation was done on a spreadsheet with 5,000 iterations.
- Tornado Diagram: This graphically displays the result of single-factor sensitivity analysis. This lets one evaluate the risk associated with the uncertainty in each of the variables that affect the outcome. Single-factor analysis means that we measure the effect on the outcome of each factor, one at a time, while holding the others at their nominal (or base) value. Each factor is adjusted between the specified minimum (or low) and maximum (or high) values while recording the value of the outcome. It then plots the resulting data in a bar chart. The uncertainty in the parameter associated with the largest bar, the one at the top of the chart, has the maximum impact on the result, with each successive lower bar having a lesser impact. In this study, the effect of the following parameters on the NPV was evaluated: initial capital, CAPEX depreciation, operating expenditure, number of students enrolled, school fees, and loan interest rate. The ranges shown in Fig 1 were used.
Outcome of the Alternatives
- Deterministic Analysis:
![]() |
Fig 2 |
- Monte Carlo Simulation:
![]() |
Fig 3 |
- Tornado Diagram:
![]() |
Fig 4 |
Selection Criteria
The following objectives were set for the analysis:
- Deterministic Analysis: NPV & IRR should be positive for all three cases
- Monte Carlo Simulation: Yearly profit should be positive between 20% to 40% range of the cumulative probability curve.
- Tornado Diagram: NPV should remain positive for both the high and low range for all the variables
Analysis of Alternatives
- Deterministic Analysis:
The results of the Deterministic Analysis in fig 2 shows that NPV and IRR is positive for both the ‘Best Case’ and ‘Most Likely Case’ while NPV and IRR are negative for the ‘Worst Case’.
- Monte Carlo Simulation:
The result of the Monte Carlo Simulation in fig 3 shows that within the 20% to 40% range of cumulative probability curve, the yearly profit remains positive ranging between N6MM and N14MM per annum.
- Tornado Diagram:
The Tornado diagram in fig 4 shows the effect of six parameters on the NPV. The result shows that “CAPEX depreciation per annum” has the maximum impact on NPV, while “loan interest” has the least impact. It also shows that the NPV remains positive for both the high and low range for all the variables.
Alternative Selected or Decision
Based on the analysis above, most of the three objectives or criteria were met except that for the deterministic analysis, NPV and IRR were negative for the ‘Worst Case’ scenario. Base on this analysis, a decision was made to move the project forward using the ‘Most Likely’ estimates as the project base case, however strict fiscal policies will be put in place to ensure that the project does not get to the ‘Worst Case’ scenario.
Performance Monitoring
1. Ensure strict fiscal policies so that project does not get to the ‘Worst Case’ scenario.
2. Actual CAPEX and operating cost shall be closely monitored and controlled so as not to exceed the worst case estimates in order to realize positive NPV’s and IRR.
3. Effort will be made to minimize the yearly CAPEX depreciation as reasonably possible because it has the greatest impact on NPV.
References
1. Engineering Economy, 14th Edition. William G. Sullivan, Elin M. Wicks, C. Patrick Koelling, Chapter 1, Page 27 & Chapter 12, Page 515-567
2. Skills & Knowledge of Cost Engineering, AACE International, 5th Edition Revised, Chapters 27 & 31
3. Project Management Using Earned Value, Humpreys & Associates, Chapter 3
WOW!!! Outstanding, Biola...... I am really pleased with the progress you have made and I am especially appreciative of your leadership by example!!!
ReplyDeleteKeep up the good work and let's see if we can get the rest of the team back on the bus in the remaining weeks!!!
BR,
Dr. PDG, Jakarta